| CCC Dulces Nombres Pesquería, NL, Mexico | Quantum Energía | 250 MW | Single-Shaft Combined Cycle | Full MEM-migration grid code campaign plus dynamic-model authoring in PSS®E and EMTP. Night-shift campaign. | COD |
| CCC Salamanca Guanajuato, Mexico | Mitsubishi Power | 980 MW | Combined Cycle | 25 grid code tests for COD. Full plant testing including AVR, governor, performance, protections, PQ. | COD |
| CCC González Ortega Mexicali, B.C., Mexico | Siemens | 900 MW | Combined Cycle | 8 grid code tests across performance, electrical protections and power quality for COD. | COD |
| CCC Mérida Yucatán, Mexico | Mitsubishi Power | 500 MW | Combined Cycle | 25 grid code tests for COD. Full plant testing across all disciplines. | COD |
| Bajío Combined Cycle Mexico | SAAVI Energy | 500 MW | GE 11 Steam Turbine | Evaluation of opening/closing of final control elements. CENACE/CFE compliant. | Completed |
| CCC Altamira Altamira, Mexico | Valia Energía | 500 MW | Combined Cycle | Per-unit and per-plant for MEM migration. Heat consumption, start-up/shut-down costs. | In Progress |
| CCC San Luis Potosí Villa de Reyes, Mexico | Mitsubishi Power | 460 MW | Combined Cycle | 25 grid code tests for COD. Full plant testing. | COD |
| CCI Mexicali Oriente Baja California, Mexico | Wärtsilä | 440 MW | Combustion Engines | Full 45 tests — AVR, governor, performance, electrical protections, power quality. COD. | COD |
| CCI Parque Industrial Baja California, Mexico | Wärtsilä | 240 MW | Combustion Engines | Full 45 tests across all disciplines. COD. | COD |
| Costa Sur Puerto Rico | GENERA | 300 MW | Steam Turbine · Upgrade | Voltage and frequency control testing for upgraded steam turbine following interconnection requirements. | COD |
| ENERTEK Altamira, Mexico | Iberdrola | 300 MW | Steam Turbine · Upgrade | Voltage and frequency control testing for upgraded steam turbine. | Completed |
| CCC Saltillo Mexico | Valia Energía | 300 MW | Combined Cycle | Per-unit and per-plant for MEM migration. Heat consumption, start-up/shut-down costs. | In Progress |
| Dulces Nombres Mexico | Iberdrola | 250 MW | Single-shaft Combined Cycle | Full 45 CENACE grid code tests. Reports created and accepted by CENACE. | Completed |
| Tuxpan V Combined Cycle Mexico | NAES | 200 MW | Mitsubishi Gas Turbines | OEL & MEL tests with Mitsubishi Electric for AVR tuning. | Completed |
| Tuxpan II Combined Cycle Mexico | NAES | 200 MW | Mitsubishi Gas Turbines | OEL & MEL evaluation for AVR system tuning with Mitsubishi Electric. | Completed |
| Central Térmica Golfo Tamuín, Mexico | AES | 170 MW | Alstom Steam Turbine · Petcoke | Grid code tests for petcoke-fired Alstom steam turbines. | Completed |
| Central Térmica Peñoles Tamuín, Mexico | AES | 170 MW | Alstom Steam Turbine · Petcoke | Grid code tests for petcoke-fired Alstom steam turbines. | Completed |
| Tractebel Cogeneration García, N.L., Mexico | ENGIE | 170 MW | GE MS7001 FA + Fuji Steam | Full 45 grid code tests for CENACE. Per-unit + interconnection point. Reports authored & accepted. | Completed |
| Cogeneración Cosoleacaque Mexico | Global Contour | 120 MW | 3 × LM6000 + Siemens Steam | Per-unit and per-plant for MEM migration. Heat consumption curves. | In Progress |
| Central Térmica Pichilingue La Paz, B.C.S., Mexico | New Fortress Energy | 120 MW | 3 × GE LM6000 Gas Turbines | Full lifecycle: Anexos III/IV, TICS, SAPPSE, grid code testing, Basler AVR tuning. | COD |
| ENGIE Pánuco Altamira, Mexico | ENGIE | 100 MW | 2 × Solar MARS + GE LM6000 | Grid code testing + Basler AVR tuning to CENACE criteria. | Completed |
| Pánuco Sugar Mill Veracruz, Mexico | Grupo Pantaleón | 45 MW | WEG Steam Turbine | 20 grid code tests for CFE/CENACE interconnection. Accepted. | Completed |
| Mante Sugar Mill Tamaulipas, Mexico | Grupo Pantaleón | 45 MW | New Steam Turbine | Technical advisory + grid code testing during commissioning. | Completed |
| CCI Megasite Ixtlahuaca Estado de México, Mexico | Telcel | 7 MW | MTU – Rolls Royce Combustion Engines · Data Center | Full 45 tests + dynamic modeling for Telcel data-center power plant. | In Progress |
| Rebasa Planta Monclova Monclova, Mexico | Rebasa | 5 MW | 2 × Caterpillar Combustion | Full 45 CENACE tests. Industrial plant with grid export. | In Progress |
| LFGE Cadereyta Nuevo León, Mexico | LFGE | 1 MW | Jenbacher Combustion Engines | Full 45 CENACE tests for new biogas plant from landfill. | COD |
| LFGE García Nuevo León, Mexico | LFGE | 1 MW | Jenbacher Combustion Engines | Full 45 CENACE tests for new biogas plant. | COD |
| CCC Tuxpan Fase I Veracruz, Mexico | Siemens | 900 MW | Combined Cycle | Inrush current measurement for first energization of step-up transformers. | Completed |