Independent grid code testing · For global utilities, IPPs and OEMs
Home/ Behind the Grid/ Plant performance/ Start-up and shutdown

Start-up and shutdown times and costs: what gets measured, and what goes wrong.

A combined-cycle plant's start-up and shutdown sequences are the most operationally complex hours in its life — and they are where the most expensive measurement errors happen.

The start-up sequence

From operator command to dispatch-stable output · Measured continuously throughout

t = 0

Command-to-roll

Operator initiates start command. Purge cycle, ignition, acceleration to firing speed.

t + 5–15 min

Firing-to-sync

Gas turbine accelerates on combustion. AVR field applied. Generator breaker closes.

t + 15–45 min

MW ramp profile

From breaker closure to minimum stable load. Bounded by thermal stress limits.

t + 30–90 min

Steam-cycle bring-on

HRSG produces useful steam. Steam turbine sync. Plant reaches full coordination.

t + 60–120 min

Dispatch-stable

Plant at dispatch-commanded output. Coordinated combined-cycle operation.

In steady-state operation a 900 MW combined-cycle plant is, broadly, a known quantity. The hours when the plant is starting up and shutting down are different. Fuel goes in but no electricity comes out for the first thirty to a hundred minutes. Hot-gas-path components see thermal cycles the OEM tracks individually.

Those hours are also where the dispatch economics turn on a few specific numbers — and where field test campaigns most often produce measurement errors. The system operator wants the start-up cost in monetary terms per start, the start-up time in minutes from command to grid-synchronous output, the shutdown cost per shutdown, and the equivalent figures for each starting state.

Three starting states · Cold, warm, hot.

State 01 · Coldest

Cold start

48+ hours offline
Highest fuel consumption per start
Longest time-to-sync
Highest component-wear cost
State 02 · Mid

Warm start

8–48 hours offline
Partial cool-down
Intermediate fuel, time, wear
Most common operational state
State 03 · Lowest

Hot start

Under 8 hours offline
Lowest fuel per start
Fastest time-to-sync
Lowest component wear

The regulator wants all three measured, because the dispatch decision changes based on starting state. A plant in a hot state can be brought online quickly and cheaply; a plant in cold state cannot. The system operator uses these numbers to decide whether dispatching a particular plant is economically sensible given current market conditions.

Field testing all three states means running three separate start-up sequences, each from the correct thermal baseline. This is calendar-expensive. Coordinating with the grid to take a working plant offline long enough to reach a cold state is rarely possible — most cold-start measurements are taken during scheduled outage returns.

CCC Salamanca · Mitsubishi combined cycle at nightWhere the bottoming cycle catches up to the gas turbine

The five failure modes that recur in start-up campaigns.

01

Fuel not measured during the no-output window

The plant burns fuel before exporting any MW. If the test only measures fuel and output together, start-up fuel is uncounted. Reported start-up cost is far below the actual cost.

Most common
02

Auxiliary load definition shifts between start-up and steady-state

HRSG fans, lube-oil systems, feedwater pumps coming online — different from steady-state. The boundary used for steady-state heat-rate measurement may be wrong for start-up.

Easy fix
03

Start-up state misclassified relative to the OEM definition

Plant offline 30 hours classified as "cold" when OEM defines it as warm. Cost offer over-estimates. Plant skipped over in conditions where it could have profitably run.

Subtle
04

Combined-cycle bring-on misattributed

Gas turbine produces export power minutes after sync; steam turbine takes 30–60 more. Treating the plant as a single block under-credits early gas-turbine output.

Combined-cycle only
05

OEM component wear cost not in the dispatch offer

The most expensive failure mode. Start-up wears equipment. OEM bills it. If the offer only contains fuel + auxiliary, the plant bids below true marginal cost. Years later, maintenance reserve is underfunded.

Most expensive

A combined-cycle plant entering a wholesale market for the first time, or a plant being re-characterized for an updated dispatch profile, needs a start-up and shutdown campaign in addition to the steady-state heat-consumption campaign. The two campaigns share instrumentation and personnel but have different measurement protocols, different time scales, and different deliverables.

For owners reading this in advance of commissioning: budget for the start-up campaign as a distinct line item. It is not a footnote on the heat-rate test. It is a separate engagement with its own calendar, its own field events, and its own dossier section.

The hours when the plant is starting and stopping are the hours when the dispatch economics get decided for the asset's life. Treating them as measurement footnotes is among the most expensive habits in plant operations.

Verify against published regulation

The start-up/shutdown protocol codified for the wholesale market in question (Mexico's CENACE expects this evidence under the MEM migration dossier; ASME PTC 22 and PTC 46 inform the test methodology in most jurisdictions), the precise definitions of cold/warm/hot starting states (typically 48+ / 8–48 / <8 hours offline in many markets, but the OEM contract values govern), and whether the regulator's dispatch algorithm accepts component-wear cost in the offer should be confirmed against the active framework. The five-failure-mode framework reflects general industry experience; regulator-specific parameters should be confirmed.

Entering a wholesale market? Plan the start-up campaign as a distinct line item.